Easy Hotel
Construction of a new-build hotel located in the Sant Andreu district of Barcelona. The building is developed between party walls and comprises a total of 80 rooms.
With a reinforced concrete structure featuring one-way slabs and load-bearing walls, the building was constructed in compliance with the Special Urban Planning Plan for Tourist Accommodation (PEUAT), maintaining the 150 hotel beds assigned under a previous licence. It includes a basement level used for parking, a ground floor, a mezzanine, 5 standard floors and a rooftop level dedicated to building services.
- Year: 2023-2025
- Duration (months): 18
- Location: Bofarull 4-6, Barcelona
- Surface area (m2): 2.814
- Developer: Privat
- Architecture: CMV Architecture
- Photography: argotphoto
- Project Management: Albion Management
- Site Management: Rossell-Giner i Associats
- Structural Engineering: BAC Engineering
- MEP & Fire Protection: International Hospitality Projects
Cardoner Instal·lacions, Cardoner Green, Fusteria del Cardoner
Integration of the proposal on a complex plot
- Project constrained by the presence of neighbouring building foundations.
- Substantial modification of the project to adapt the design to the actual on-site layout.
An eco-efficient project
- The project applies the criteria set out in Decree 21/2006 on eco-efficiency, including compliance with thermal-transmittance requirements for vertical enclosures, water-consumption efficiency through low-flow taps, selective domestic-waste management, and the use of solar-thermal energy for domestic hot-water (DHW) production.
Design and implementation of building services
- Centralised HVAC system.
- Solar-thermal energy system for DHW production.
- Selective waste-collection system by fractions.
- Parking facility with vehicle lift.